BetaActiveSolarMISOLBNL + Live
23.4 MW generation in Muscatine, IA · In queue since December 2021 · Proposed COD July 2024
23.4 MW
Capacity
1
Components
Solar
4y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 7m
Schedule
21 months past proposed COD
In Study38%
Queue EntryDec 3, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-07-15
Project Details
State
IA
County
Muscatine
Region
MISO
Developer
—
Utility
MUSCATINE POWER AND WATER
Entity
MISO
Point of Interconnection
Grandview Substation 69 kV
Data Source
LBNL + Live
No news available for this project.