— Project Summary

Queue ID
MISO-J1927
Capacity
23.4 MW
Technology
Solar
Status
active
Location
Muscatine, IA
Region
MISO
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarMISOLBNL + Live

23.4 MW generation in Muscatine, IA · In queue since December 2021 · Proposed COD July 2024

23.4 MW

Capacity

1

Components

Solar

4y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 7m

Schedule

21 months past proposed COD

In Study38%
Queue EntryDec 3, 2021

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-07-15

Project Details

State

IA

County

Muscatine

Region

MISO

Developer

Utility

MUSCATINE POWER AND WATER

Entity

MISO

Point of Interconnection

Grandview Substation 69 kV

Data Source

LBNL + Live

No news available for this project.