BetaActiveSolarMISOLBNL + Live
200 MW generation in Livingston, MI · In queue since August 2021 · Proposed COD November 2023
200 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Cluster Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 3m
Schedule
29 months past proposed COD
Impact Study25%
Queue EntryAug 19, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-11-01
Project Details
State
MI
County
Livingston
Region
MISO
Developer
—
Utility
ITC
Entity
MISO
Point of Interconnection
Madrid- Majestic 345 kV
Data Source
LBNL + Live