— Project Summary

Queue ID
MISO-J1895
Capacity
200 MW
Technology
Battery
Status
active
Location
Kenosha, WI
Region
MISO
Developer
IA Status
Cluster Study

BetaActiveBatteryMISOLBNL + Live

200 MW storage in Kenosha, WI · In queue since October 2023 · Proposed COD September 2024

200 MW

Capacity

1

Components

Battery

2y 5m

In Queue

Cluster Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

11 months

Schedule

18 months past proposed COD

Impact Study25%
Queue EntryOct 3, 2023

Interconnection request submitted to ISO/RTO

DPP StudyCurrent

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-30

Project Details

State

WI

County

Kenosha

Region

MISO

Developer

Utility

AMERICAN TRANSMISSION COMPANY

Entity

MISO

Point of Interconnection

Balsam

Data Source

LBNL + Live

No news available for this project.