BetaActiveBatteryMISOLBNL + Live
60 MW storage in Ottawa, MI · In queue since August 2021 · Proposed COD September 2024
60 MW
Capacity
1
Components
Battery
4y 7m
In Queue
Cluster Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 1m
Schedule
19 months past proposed COD
Impact Study25%
Queue EntryAug 16, 2021
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-15
Project Details
State
MI
County
Ottawa
Region
MISO
Developer
—
Utility
METC
Entity
MISO
Point of Interconnection
Argenta to Tallmadge 345kV (33 miles from Argenta)
Data Source
LBNL + Live
No news available for this project.