BetaActiveBatteryMISOLBNL + Live
100 MW storage in Washtenaw, MI · In queue since December 2020 · Proposed COD October 2024
100 MW
Capacity
1
Components
Battery
5y 3m
In Queue
Cluster Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 10m
Schedule
18 months past proposed COD
Impact Study25%
Queue EntryDec 31, 2020
Interconnection request submitted to ISO/RTO
DPP StudyCurrent
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-10-07
Project Details
State
MI
County
Washtenaw
Region
MISO
Developer
—
Utility
ITC
Entity
MISO
Point of Interconnection
19CVTRY
Data Source
LBNL + Live
No news available for this project.