BetaActiveCoalMISOLBNL
550 MW generation in IL · In queue since December 2001 · Proposed COD June 2002
550 MW
Capacity
1
Components
Coal
24y 3m
In Queue
IA Executed
IA Status
COD target: 2002
Interconnection Timeline
Total Duration
6 months
Schedule
290 months past proposed COD
Construction75%
Queue EntryDec 2, 2001
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2002-06-01
Project Details
State
IL
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Unknown
Data Source
LBNL