135 MW generation in OH · In queue since May 2008 · Proposed COD January 2010
135 MW
Capacity
1
Components
Gas
17y 10m
In Queue
IA Executed
IA Status
COD target: 2010
Interconnection Timeline
Total Duration
1y 8m
Schedule
198 months past proposed COD
Construction75%
Queue EntryMay 29, 2008
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2010-01-01
Project Details
State
OH
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Millard Road and Tiffin Drive, Ironville Substation
Data Source
LBNL
No news available for this project.