BetaActiveCoalMISOLBNL
42 MW generation in IL · In queue since March 2008 · Proposed COD March 2015
42 MW
Capacity
1
Components
Coal
18 years
In Queue
IA Executed
IA Status
COD target: 2015
Interconnection Timeline
Total Duration
7 years
Schedule
134 months past proposed COD
Construction75%
Queue EntryMar 17, 2008
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2015-03-30
Project Details
State
IL
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
AEG Newton Unit 1 345kV
Data Source
LBNL
No news available for this project.