— Project Summary

Queue ID
MISO-G343
Capacity
20 MW
Technology
Other
Status
active
Location
MI
Region
MISO
Developer
IA Status
IA Executed

BetaActiveOtherMISOLBNL

20 MW generation in MI · In queue since June 2003 · Proposed COD May 2002

20 MW

Capacity

1

Components

Other

22y 9m

In Queue

IA Executed

IA Status

COD target: 2002

Interconnection Timeline

Total Duration

22y 9m

Schedule

291 months past proposed COD

Construction75%
Queue EntryJun 1, 2003

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–36 months

Commercial Operation

Proposed COD: 2002-05-01

Project Details

State

MI

County

Region

MISO

Developer

Utility

Entity

MISO

Point of Interconnection

Warden Gen Station

Data Source

LBNL

No news available for this project.