— Project Summary

Queue ID
MISO-G177
Capacity
5 MW
Technology
Other
Status
active
Location
MN
Region
MISO
Developer
IA Status
IA Executed

BetaActiveUnknownMISOLBNL

5 MW generation in MN · In queue since March 2002 · Proposed COD June 2004

5 MW

Capacity

1

Components

Unknown

24 years

In Queue

IA Executed

IA Status

COD target: 2004

Interconnection Timeline

Total Duration

2y 3m

Schedule

266 months past proposed COD

Construction75%
Queue EntryMar 4, 2002

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–36 months

Commercial Operation

Proposed COD: 2004-06-01

Project Details

State

MN

County

Region

MISO

Developer

Utility

Entity

MISO

Point of Interconnection

Unknown

Data Source

LBNL

No news available for this project.