BetaActiveCoalMISOLBNL
174 MW generation in KY · In queue since December 1998 · Proposed COD January 2004
174 MW
Capacity
1
Components
Coal
27y 3m
In Queue
IA Executed
IA Status
COD target: 2004
Interconnection Timeline
Total Duration
5y 1m
Schedule
271 months past proposed COD
Construction75%
Queue EntryDec 1, 1998
Interconnection request submitted to ISO/RTO
DPP Study
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2004-01-01
Project Details
State
KY
County
—
Region
MISO
Developer
—
Utility
—
Entity
MISO
Point of Interconnection
Unknown
Data Source
LBNL
No news available for this project.