— Project Summary

Queue ID
MISO
Capacity
50 MW
Technology
Wind
Status
active
Location
Lawrence, MS
Region
MISO
Developer
IA Status

BetaActiveWindMISOLBNL

50 MW generation in Lawrence, MS · In queue since April 2024 · Proposed COD October 2027

50 MW

Capacity

1

Components

Wind

1y 11m

In Queue

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 6m

Pre-Study0%
Queue EntryApr 17, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-01

Project Details

State

MS

County

Lawrence

Region

MISO

Developer

Utility

Entity

MISO

Point of Interconnection

GP-Monticello

Data Source

LBNL

No news available for this project.