BetaActiveSolarBatteryLGE-KULBNL
75 MW hybrid in Grayson, KY · In queue since January 2024 · Proposed COD December 2027
75 MW
Capacity
1
Components
Solar
2y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 11m
In Study38%
Queue EntryJan 23, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
KY
County
Grayson
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Ohio Co_x0013_Leitchfield 69 kV Line
Data Source
LBNL
No news available for this project.