BetaActiveSolarLGE-KULBNL
138 MW generation in Hopkins, KY · In queue since August 2023 · Proposed COD December 2026
138 MW
Capacity
1
Components
Solar
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 4m
In Study38%
Queue EntryAug 21, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-12
Project Details
State
KY
County
Hopkins
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
161kV Earlington North Substation
Data Source
LBNL
No news available for this project.