— Project Summary

Queue ID
LGE-KU-LGE-GIS-2023-006
Capacity
125 MW
Technology
Solar+Battery
Status
active
Location
Daviess, KY
Region
Southeast
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryLGE-KULBNL

125 MW hybrid in Daviess, KY · In queue since July 2023 · Proposed COD September 2027

125 MW

Capacity

1

Components

Solar

2y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 2m

In Study38%
Queue EntryJul 24, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-01

Project Details

State

KY

County

Daviess

Region

Southeast

Developer

Utility

Louisville Gas & Electric and Kentucky Utilities Energy

Entity

LGE-KU

Point of Interconnection

Zion to Green River Steel 69kV line

Data Source

LBNL

No news available for this project.