BetaActiveSolarLGE-KULBNL
100 MW generation in Caldwell, KY · In queue since June 2023 · Proposed COD March 2026
100 MW
Capacity
1
Components
Solar
2y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 9m
In Study38%
Queue EntryJun 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-31
Project Details
State
KY
County
Caldwell
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
North Princeton 161kV Substation
Data Source
LBNL
No news available for this project.