BetaActiveSolarBatteryLGE-KULBNL
89 MW hybrid in Mercer, KY · In queue since May 2023 · Proposed COD September 2027
89 MW
Capacity
1
Components
Solar
2y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 4m
In Study38%
Queue EntryMay 2, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-01
Project Details
State
KY
County
Mercer
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Harrodsburg _x0013_ West Cliff 69 kV line
Data Source
LBNL