BetaActiveBatteryLGE-KULBNL
125 MW storage in Mercer, KY · In queue since April 2023 · Proposed COD December 2026
125 MW
Capacity
1
Components
Battery
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 8m
In Study38%
Queue EntryApr 20, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
KY
County
Mercer
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Brown North Substation 345 kV bus.
Data Source
LBNL
No news available for this project.