660 MW generation in Mercer, KY · In queue since April 2023 · Proposed COD April 2028
660 MW
Capacity
1
Components
Gas
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5 years
In Study38%
Queue EntryApr 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-01