660 MW generation in Jefferson, KY · In queue since June 2022 · Proposed COD April 2027
660 MW
Capacity
1
Components
Gas
3y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 10m
In Study38%
Queue EntryJun 21, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-01
Project Details
State
KY
County
Jefferson
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Mill Creek Substation 345 kV bus
Data Source
LBNL