BetaActiveSolarLGE-KULBNL
40 MW generation in Wise, VA · In queue since May 2022 · Proposed COD June 2025
40 MW
Capacity
1
Components
Solar
3y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 1m
Schedule
10 months past proposed COD
In Study38%
Queue EntryMay 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-01
Project Details
State
VA
County
Wise
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Dorchester to Blackwood 69 kV line
Data Source
LBNL
No news available for this project.