19.98 MW generation in Wise, VA · In queue since October 2021 · Proposed COD December 2024
19.98 MW
Capacity
1
Components
Solar
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 2m
Schedule
15 months past proposed COD
In Study38%
Queue EntryOct 6, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
VA
County
Wise
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Dorchester to Blackwood 69 kV line
Data Source
LBNL