BetaActiveSolarBatteryLGE-KULBNL
120 MW hybrid in Mccracken, KY · In queue since June 2021 · Proposed COD December 2023
120 MW
Capacity
1
Components
Solar
4y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 6m
Schedule
27 months past proposed COD
In Study38%
Queue EntryJun 24, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-31
Project Details
State
KY
County
Mccracken
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Primary: Grahamville 161 kV bus; Alternate: Grahamville _x0013_ Wickliffe 161 kV line
Data Source
LBNL
No news available for this project.