BetaActiveSolarLGE-KULBNL
100 MW generation in Boyle, KY · In queue since May 2021 · Proposed COD June 2027
100 MW
Capacity
1
Components
Solar
4y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 1m
In Study38%
Queue EntryMay 10, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
KY
County
Boyle
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Primary: KY ST Hospital Substation 69 kV Bus; Alternate: KY ST Hospital Tap - Danville E 69 kV line
Data Source
LBNL
No news available for this project.