BetaActiveBatteryLGE-KULBNL
300 MW storage in Jefferson, KY · In queue since March 2021 · Proposed COD December 2026
300 MW
Capacity
1
Components
Battery
5 years
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 9m
Construction75%
Queue EntryMar 25, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
KY
County
Jefferson
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Mill Creek 138 KV substation
Data Source
LBNL
No news available for this project.