BetaSuspendedSolarBatteryLGE-KULBNL
200 MW hybrid in Hardin, KY · In queue since March 2021 · Proposed COD June 2026
200 MW
Capacity
1
Components
Solar
5 years
In Queue
Suspended
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 3m
Suspended38%
Queue EntryMar 22, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-15
Project Details
State
KY
County
Hardin
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Primary: Hardin County 345 kV bus; Alternate: Hardin County _x0013_ Daviess County 345 kV line, SIS Primary changed to: Hardin County _x0013_ Daviess County 345 kV line
Data Source
LBNL
No news available for this project.