BetaSuspendedSolarLGE-KULBNL
50 MW generation in Madison, KY · In queue since October 2020 · Proposed COD December 2024
50 MW
Capacity
1
Components
Solar
5y 5m
In Queue
Suspended
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
4y 2m
Suspended38%
Queue EntryOct 2, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
KY
County
Madison
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Lake Reba - West Irvine Line Tap 161 kV
Data Source
LBNL
No news available for this project.