— Project Summary

Queue ID
LGE-KU-LGE-GIS-2019-029 3
Capacity
100 MW
Technology
Solar
Status
suspended
Location
Hardin, KY
Region
Southeast
Developer
IA Status
Suspended

BetaSuspendedSolarLGE-KULBNL

100 MW generation in Hardin, KY · In queue since November 2019 · Proposed COD December 2024

100 MW

Capacity

1

Components

Solar

6y 4m

In Queue

Suspended

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

5y 1m

Suspended38%
Queue EntryNov 8, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

KY

County

Hardin

Region

Southeast

Developer

Utility

Louisville Gas & Electric and Kentucky Utilities Energy

Entity

LGE-KU

Point of Interconnection

Black Branch- Hardinsburg 138 kV

Data Source

LBNL

No news available for this project.