98.42 MW generation in Mercer, KY · In queue since May 2019 · Proposed COD October 2026
98.42 MW
Capacity
1
Components
Solar
6y 10m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 5m
Construction75%
Queue EntryMay 2, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-10-01
Project Details
State
KY
County
Mercer
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Bardstown - Brown CT 138 kV Line
Data Source
LBNL