104 MW generation in Ballard, KY · In queue since February 2019 · Proposed COD September 2026
104 MW
Capacity
1
Components
Solar
7y 1m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 7m
Construction75%
Queue EntryFeb 6, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-09-30
Project Details
State
KY
County
Ballard
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Grahamville _x0013_ Wickliffe 161 kV Line
Data Source
LBNL