BetaActiveSolarLGE-KULBNL
86 MW generation in Lyon, KY · In queue since March 2017 · Proposed COD May 2024
86 MW
Capacity
1
Components
Solar
9 years
In Queue
IA Executed
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
7y 2m
Schedule
23 months past proposed COD
Construction75%
Queue EntryMar 1, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2024-05-01
Project Details
State
KY
County
Lyon
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
North Princeton - Livingston Co 161 kV
Data Source
LBNL
No news available for this project.