BetaActiveSolarLGE-KULBNL
10 MW generation in Mercer, KY · In queue since August 2014 · Proposed COD January 2016
10 MW
Capacity
1
Components
Solar
11y 7m
In Queue
IA Executed
IA Status
COD target: 2016
Interconnection Timeline
Total Duration
1y 5m
Schedule
125 months past proposed COD
Construction75%
Queue EntryAug 22, 2014
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2016-01-01
Project Details
State
KY
County
Mercer
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Brown Plant on the 138 kV side
Data Source
LBNL
No news available for this project.