691 MW hybrid in Jefferson, KY · In queue since August 2013 · Proposed COD March 2015
691 MW
Capacity
1
Components
Gas
12y 7m
In Queue
IA Executed
IA Status
COD target: 2015
Interconnection Timeline
Total Duration
1y 7m
Schedule
135 months past proposed COD
Construction75%
Queue EntryAug 23, 2013
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2015-03-01
Project Details
State
KY
County
Jefferson
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Cane Run Switching Station 138 kV uprate
Data Source
LBNL