BetaActiveHydroLGE-KULBNL
21 MW generation in Jefferson, KY · In queue since February 2011 · Proposed COD January 2013
21 MW
Capacity
1
Components
Hydro
15y 1m
In Queue
IA Executed
IA Status
COD target: 2013
Interconnection Timeline
Total Duration
1y 11m
Schedule
161 months past proposed COD
Construction75%
Queue EntryFeb 22, 2011
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2013-01-01
Project Details
State
KY
County
Jefferson
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Ohio Falls Uprate
Data Source
LBNL
No news available for this project.