— Project Summary

Queue ID
LGE-KU-LGE-GIS-2010-001
Capacity
690 MW
Technology
Gas
Status
active
Location
Jefferson, KY
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveGasLGE-KULBNL

690 MW generation in Jefferson, KY · In queue since April 2010 · Proposed COD March 2015

690 MW

Capacity

1

Components

Gas

15y 11m

In Queue

IA Executed

IA Status

COD target: 2015

Interconnection Timeline

Total Duration

4y 11m

Schedule

135 months past proposed COD

Construction75%
Queue EntryApr 7, 2010

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2015-03-01

Project Details

State

KY

County

Jefferson

Region

Southeast

Developer

Utility

Louisville Gas & Electric and Kentucky Utilities Energy

Entity

LGE-KU

Point of Interconnection

Cane Run Switching Station 138 kV

Data Source

LBNL

No news available for this project.