BetaActiveGasLGE-KULBNL
690 MW generation in Jefferson, KY · In queue since April 2010 · Proposed COD March 2015
690 MW
Capacity
1
Components
Gas
15y 11m
In Queue
IA Executed
IA Status
COD target: 2015
Interconnection Timeline
Total Duration
4y 11m
Schedule
135 months past proposed COD
Construction75%
Queue EntryApr 7, 2010
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2015-03-01
Project Details
State
KY
County
Jefferson
Region
Southeast
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Point of Interconnection
Cane Run Switching Station 138 kV
Data Source
LBNL
No news available for this project.