1,000 MW hybrid in Los Angeles, CA · In queue since March 2023 · Proposed COD November 2030
1,000 MW
Capacity
1
Components
Solar
3 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 8m
In Study38%
Queue EntryMar 2, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-11-30
Project Details
State
CA
County
Los Angeles
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Haynes 230kV Switchyard
Data Source
LBNL