— Project Summary

Queue ID
LADWP-Q96
Capacity
1000 MW
Technology
Solar+Battery
Status
active
Location
Los Angeles, CA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryLADWPLBNL

1,000 MW hybrid in Los Angeles, CA · In queue since March 2023 · Proposed COD November 2030

1,000 MW

Capacity

1

Components

Solar

3 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

7y 8m

In Study38%
Queue EntryMar 2, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-11-30

Project Details

State

CA

County

Los Angeles

Region

West

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

Scattergood 230kV Switchyard

Data Source

LBNL

No news available for this project.