— Project Summary

Queue ID
LADWP-Q95
Capacity
346 MW
Technology
Other
Status
active
Location
Los Angeles, CA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveHydrogenLADWPLBNL

346 MW generation in Los Angeles, CA · In queue since January 2023 · Proposed COD January 2030

346 MW

Capacity

1

Components

Hydrogen

3y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

7 years

In Study38%
Queue EntryJan 19, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-01-01

Project Details

State

CA

County

Los Angeles

Region

West

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

Scattergood 230kV Switchyard

Data Source

LBNL

No news available for this project.