— Project Summary

Queue ID
LADWP-Q92
Capacity
1650 MW
Technology
Solar+Battery
Status
active
Location
San Bernardino, CA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryLADWPLBNL

1,650 MW hybrid in San Bernardino, CA · In queue since June 2022 · Proposed COD December 2025

1,650 MW

Capacity

1

Components

Solar

3y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 6m

Schedule

3 months past proposed COD

In Study38%
Queue EntryJun 20, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

CA

County

San Bernardino

Region

West

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

Adelanto 500 KV Switchyard

Data Source

LBNL

No news available for this project.