BetaActiveSolarBatteryLADWPLBNL
1,650 MW hybrid in San Bernardino, CA · In queue since June 2022 · Proposed COD December 2025
1,650 MW
Capacity
1
Components
Solar
3y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 6m
Schedule
3 months past proposed COD
In Study38%
Queue EntryJun 20, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
CA
County
San Bernardino
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Adelanto 500 KV Switchyard
Data Source
LBNL
No news available for this project.