BetaActiveSolarBatteryLADWPLBNL
1,000 MW hybrid in Clark, NV · In queue since April 2022 · Proposed COD December 2028
1,000 MW
Capacity
2
Components
Solar + Battery
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
6y 8m
In Study38%
Queue EntryApr 1, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-28
Technology
Solar500 MW · 50%
Battery500 MW · 50%
Project Details
State
NV
County
Clark
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Marketplace 500kV
Data Source
LBNL