BetaActiveBatteryLADWPLBNL
300 MW storage in Los Angeles, CA · In queue since July 2021 · Proposed COD May 2024
300 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 10m
Schedule
22 months past proposed COD
In Study38%
Queue EntryJul 29, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-05-30
Project Details
State
CA
County
Los Angeles
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Gramercy-Harbor 138kV Line
Data Source
LBNL
No news available for this project.