— Project Summary

Queue ID
LADWP-Q82
Capacity
300 MW
Technology
Battery
Status
active
Location
Los Angeles, CA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryLADWPLBNL

300 MW storage in Los Angeles, CA · In queue since July 2021 · Proposed COD May 2024

300 MW

Capacity

1

Components

Battery

4y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 10m

Schedule

22 months past proposed COD

In Study38%
Queue EntryJul 29, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-05-30

Project Details

State

CA

County

Los Angeles

Region

West

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

Gramercy-Harbor 138kV Line

Data Source

LBNL

No news available for this project.