590 MW hybrid in Kern, CA · In queue since April 2021 · Proposed COD February 2024
590 MW
Capacity
2
Components
Solar + Battery
4y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 10m
Schedule
26 months past proposed COD
In Study38%
Queue EntryApr 7, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-02-01
Technology
Solar350 MW · 59%
Battery240 MW · 41%
Project Details
State
CA
County
Kern
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Barren Ridge 230 kV Sw Station
Data Source
LBNL