BetaActiveOther StorageLADWPLBNL
500 MW storage in Kern, CA · In queue since October 2020 · Proposed COD August 2021
500 MW
Capacity
1
Components
Other Storage
5y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
10 months
Schedule
57 months past proposed COD
In Study38%
Queue EntryOct 2, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-08-01
Project Details
State
CA
County
Kern
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Rosamond 230kV Switching Station
Data Source
LBNL
No news available for this project.