— Project Summary

Queue ID
LADWP-Q75
Capacity
225 MW
Technology
Solar+Battery
Status
active
Location
Kern, CA
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryLADWPLBNL

225 MW hybrid in Kern, CA · In queue since January 2020 · Proposed COD December 2022

225 MW

Capacity

2

Components

Solar + Battery

6y 2m

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 11m

Schedule

40 months past proposed COD

Impact Study25%
Queue EntryJan 7, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-01

Technology
Solar150 MW · 67%
Battery75 MW · 33%
Project Details

State

CA

County

Kern

Region

West

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

Rosamond 230kV Switching Station

Data Source

LBNL

No news available for this project.