BetaActiveBatteryLADWPLBNL
200 MW storage in Los Angeles, CA · In queue since July 2019 · Proposed COD November 2023
200 MW
Capacity
1
Components
Battery
6y 8m
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
4y 4m
Schedule
28 months past proposed COD
Impact Study25%
Queue EntryJul 31, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-11-30
Project Details
State
CA
County
Los Angeles
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Fairfax 138kV Substation
Data Source
LBNL
No news available for this project.