BetaActiveSolarBatteryLADWPLBNL
400 MW hybrid in San Bernardino, CA · In queue since July 2019 · Proposed COD November 2021
400 MW
Capacity
2
Components
Solar + Battery
6y 8m
In Queue
Facility Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 4m
Schedule
53 months past proposed COD
Facilities Study50%
Queue EntryJul 22, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-11-05
Technology
Solar200 MW · 50%
Battery200 MW · 50%
Project Details
State
CA
County
San Bernardino
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Adelanto 500kV Substation
Data Source
LBNL
No news available for this project.