— Project Summary

Queue ID
LADWP-Q72
Capacity
400 MW
Technology
Solar+Battery
Status
active
Location
San Bernardino, CA
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatteryLADWPLBNL

400 MW hybrid in San Bernardino, CA · In queue since July 2019 · Proposed COD November 2021

400 MW

Capacity

2

Components

Solar + Battery

6y 8m

In Queue

Facility Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

2y 4m

Schedule

53 months past proposed COD

Facilities Study50%
Queue EntryJul 22, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-11-05

Technology
Solar200 MW · 50%
Battery200 MW · 50%
Project Details

State

CA

County

San Bernardino

Region

West

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

Adelanto 500kV Substation

Data Source

LBNL

No news available for this project.