300 MW storage in Los Angeles, CA · In queue since May 2019 · Proposed COD November 2021
300 MW
Capacity
1
Components
Battery
6y 10m
In Queue
Facility Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 6m
Schedule
54 months past proposed COD
Facilities Study50%
Queue EntryMay 10, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-11-01
Project Details
State
CA
County
Los Angeles
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Saint John 230kV Substation
Data Source
LBNL