300 MW hybrid in San Bernardino, CA · In queue since April 2019 · Proposed COD September 2022
300 MW
Capacity
2
Components
Solar + Battery
6y 11m
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 5m
Schedule
43 months past proposed COD
Facilities Study50%
Queue EntryApr 15, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-09-15
Technology
Solar200 MW · 67%
Battery100 MW · 33%
Project Details
State
CA
County
San Bernardino
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Mead-Victorville 287kV Line
Data Source
LBNL