— Project Summary

Queue ID
LADWP-Q69
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
San Bernardino, CA
Region
West
Developer
IA Status
Facility Study

BetaActiveSolarBatteryLADWPLBNL

300 MW hybrid in San Bernardino, CA · In queue since April 2019 · Proposed COD September 2022

300 MW

Capacity

2

Components

Solar + Battery

6y 11m

In Queue

Facility Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 5m

Schedule

43 months past proposed COD

Facilities Study50%
Queue EntryApr 15, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-09-15

Technology
Solar200 MW · 67%
Battery100 MW · 33%
Project Details

State

CA

County

San Bernardino

Region

West

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

Mead-Victorville 287kV Line

Data Source

LBNL

No news available for this project.