2,400 MW hybrid in Los Angeles, CA · In queue since March 2019 · Proposed COD June 2022
2,400 MW
Capacity
2
Components
Solar + Battery
7 years
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 3m
Schedule
46 months past proposed COD
Facilities Study50%
Queue EntryMar 26, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-06-01
Technology
Solar1,200 MW · 50%
Battery1,200 MW · 50%
Project Details
State
CA
County
Los Angeles
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Rinaldi-Victorville 500kV line
Data Source
LBNL