BetaActiveSolarBatteryLADWPLBNL
500 MW hybrid in Clark, NV · In queue since March 2019 · Proposed COD December 2022
500 MW
Capacity
2
Components
Solar + Battery
7 years
In Queue
Facility Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 9m
Schedule
40 months past proposed COD
Facilities Study50%
Queue EntryMar 5, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-01
Technology
Solar250 MW · 50%
Battery250 MW · 50%
Project Details
State
NV
County
Clark
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
McCullough 230kV Substation
Data Source
LBNL
No news available for this project.